Project Summary

Annual patching program, consists of spot-pavement patching in locations throughout the city. If there are patching locations in your neighborhood, you will see signs go up in the parkway in the days leading up to the work to ensure no parking takes place in the work areas. Patches are excavated and repaved in the same day and opened back up to traffic afterwards.

LATEST UPDATE

October 20, 2023

Equipment breakdown has pushed the schedule to the week of 10/23.

PAST UPDATES

October 13, 2023

Work is expected to take place the week of 10/16.


September 29, 2023

A preconstruction meeting is planned for Friday, September 29th, at which time a schedule for work will be more clearly established.


September 22, 2023

The project was awarded at the 9/19 Council meeting. The Village is working with the contractor to determine a schedule. Work is expected to be completed by the end of October.


September 15, 2023

Bids were opened on September 6th and recommendation will be presented at the next scheduled Council meeting.


September 8, 2023

Bids were opened on September 6th and recommendation will be presented at an upcoming Council meeting.


August 25, 2023

This project was advertised for bidding on August 23rd. Bids will be opened on September 6th.

RESOURCES

Project #: ST-004D

Start: August 2023

End: September 2023

Docs/Links

MAP

PROJECT MANAGER

Stephanie Graves

Staff Engineer